Budgens
Client: Budgens, Holt
Duration: 4 weeks fit out
The Brief
The town of Holt had been living without its only supermarket for nearly 3 years, after it was destroyed by a devastating electrical fire in June 2020. With works underway to replace this essential community store, the pressure to complete construction was high. Whilst the build programme slipped through CAT A and B phases Budgens Store owner, CT Baker, was looking to make up for lost time with the store fit out.
The Project
Intensive pre-planning, a commitment to early design approval and a freeze on any subsequent design changes meant we were able to squeeze the fitout timeframe. This project was all about engineering an approach, to work at real pace. We worked with our manufacturers to ensure the retail system was produced in smaller parts, to allow for super fleet installation on site. Whilst we closely stage managed the shop floor to ensure all trades adequate space to work efficiently. We completed the store in time for its all-important opening date, where the town of Holt can now access self-service groceries and post office services, together with bakery and deli items, once more.